Projected Project Schedule

Description Start Finish
Library North 1st and 2nd floor 8/24/06 02/08/07
LN 1&2 Demo & Construction 9/18/06   01/25/07
LN1 and LN2 Occupied   02/08/07
Links 12/11/16 10/19/07
Library South 2nd floor 01/22/07 03/30/07
LS2 Demo & Construction 01/29/07 03/30/07
LS2 Occupied   04/13/07
Library North 3rd floor 02/14/07 05/25/07
Library North 4th floor West 1/2 12/12/06 03/16/07
Library North 4th floor East 1/2 04/11/07 06/25/07
Library North 5th floor West 1/2 02/02/07 05/04/07
Library North 5th floor East 1/2 06/26/07 08/29/07
Project Completion 10/04/07 11/30/07